Alpine Tunnel

Alpine Tunnel

Alpine Tunnel

Distance

2.2 mi

Technical Rating

3 Easy

Best Time

Summer, Fall

Trail Type

High-Clearance 4x4 Trail

Accessible By

Trail Overview

The Alpine Tunnel was once the highest railroad tunnel in the world. At an altitude of 11,523 feet, it was the first tunnel to be built through the Continental Divide. The Denver, South Park and Pacific Railroad began the work of connecting St Elmo to Pitkin, Colorado in November 1879 with a construction crew working at either end to connect the line.Anticipating that the mineral-rich area would be the next big mining "bonanza," as many as 10,000 different men worked to build the line and the tunnel at various times. A crew of around 400 worked steadily, but turnover was quick, as the men suffered through the cold, brutal work. Laborers, working for $3.50 per day, and explosives men, who worked for $5.00 per day, were often forced to go from their worksite to their cabins in groups in order to avoid being lost in the snow.Excavation of the tunnel began in January 1880 with plans to complete it within six months. But, those were ambitious plans, especially starting the project in the middle of winter. It would actually take the railroad more than two years to complete the tunnel and cost them far more than they had planned, coming in at about $300,000 and some $180,000 more than they had initially budgeted. Due to crumbling granite in the tunnel, over 400,000 board feet of California redwood was required to support and encase 80% of it.The two crews met each other in the tunnel in July 1881, but it would be another year before it was ready for the train.When the first narrow gauge train came through in July 1882, the tunnel was 1, 772 feet long, over two miles above sea level, 500 feet below Altman Pass (later renamed Alpine Pass), and the most expensive railroad tunnel built up until that time.Beyond the west portal exit of the tunnel, stood the alpine Tunnel Station, the highest railroad station in the nation; as well as a turntable, water tank, stone boarding house, and engine house that was large enough to house six engines.This is a short road off Hancock Pass. Access is much easier from the Pitkin side.

Weather

Status Reports

Joshua Bartels
Oct 01, 2024
2000 Jeep Wrangler
Open
Normal
Historic Alpine Tunnel Road and Palisade Wall Construction Complete The #GMUG National Forests announce the reopening of National Forest System Road (NFSR) #839–Alpine Tunnel road following the completion of a multi-year reconstruction project to restore the Palisade Wall.
Ethan P
Sep 26, 2024
4x4
Obstructed
Rock Slide about half way up the tunnel trail completely blocking the road.
Jake E
Jun 18, 2024
4x4
Temporarily Closed
Closed Gate
John Mcdonald
Mar 17, 2024
4x4
Temporarily Closed
Weather Event
Trail Restoration
An avalanche in 2022 closed OHV access to the Palisades, tunnel and interpretive site. You must now park at the turnoff to the tunnel and hike to it. Indications were that it would be reopened but when was not specified.